On the session on 19 of August our government accepts decree for assuring the resources for construction of the regional depots for public wastes on the territory of Republic of Bulgaria, including plant for the waste on the territory of the city of Sofia and also for preliminary treatment or closing (re-cultivation) of the all municipalities waste depots, which can not meet the requirements from the European Union.
Following Nona Karadjova opinion the total amount will be about 1 milliard, where about 600 mill. leva will come from Operational Programme “Environment” and rest will come from the government budget. About 733 mill. Leva will be spent for final construction of the infrastructure for waste management (mainly in that 32 regions where there is no regional depots, and funding for Sofia waste plant, 180 mill – for closing of the depots in some municipalities and 66 millions – for construction of the devices for preliminary treatment in the existing depots.
This is political attempt: 1 to solve problem with EU requirements
2. To give the municipalities equal initial conditions.
The first factory for waste treatment in
The cost of the project is 42 mill leva, where 2/3 from the amount is covered by the state and 1/3 from the
The capacity of the factory is about 125 000 tones per year
76 municipality’s depots fulfill their capacity and municipalities were starting process of recultivation. There is 60 more with low degree of risk which will be closed soon.
The plant possesses modern separating technology. The area of the plant is 224 decares. The complex includes halls for pliminary and secondary treatment, depot will 4 cells for collecting of the waste from technological cycle and administrative building. Total build up area is about 25 000 sq.m. The plant is using French technology with developer French company “Tesem”. This technology includes automatically division of the valuable materials. The waste which can not be used will be kept and after that used in construction. It takes a lot of time so to adapt technoly to the Bulgarian legislation. Developer is DZZD Consortium “Ecological plant”
The prognosticate about annual capacity is about 125 000 tones per year, where the max. capacity is about 275 000 tones. With this capacity the plant can treat the waste from following municipalities: Rodopi, Marica, Kuklen, Stamboliiski, Asenovgrad
The construction starts on 21 of May 2004, where the idea was in 2007 to be opened, but there were a lot of problems with funding which prolong the construction period.
According to EU priority for funding: on the first place are the measurements which can decrease the quantity of the waste, on second place – recycling, on the third place “thermal treatment of the waste”
About the plant in Sofia – the project consist of integrate system for waste treatment, including factory construction of the plant for mechanic and biological treatment of the daily waste, installation for separating and composting of the green waste and depot for non dangerous waste. The idea is till next year the plant to be open. According to the project after mechanical treatment of the waste the plant will produce fuel: bio diesel and bio methane.
One of the specifics of the Bulgarian garbage is that biomass and paper constitute about 60-70 % from the whole waste. The reason is that there are a lot of food waste, because in
One of the possible variant for receiving energy from the waste which is discussed is from procedure for removing the hydrogen from the fuel and burning it.
In
Till the end of 2009
According to Bulgarian legislation every year municipalities have to plan some resources for closing of the waste depots. The money for this has to be included in the annual waste tax, which each household have to pay.
Because for the small municipalities is not possible to collect enough money for such procedure there is special government programme PUDOS, which can give credit lines or to give money without return to some municipalities especially in the case when there is environment pollution.
'환경 에너지' 카테고리의 다른 글
유럽의 South Stream, Nabucco 가스송유관 프로젝트 개요 (0) | 2009.11.19 |
---|---|
EU 신가입국 신재생 에너지 도입 현황 및 진출방안 (0) | 2009.11.19 |
세계의 스마트 그리드 현황 (0) | 2009.10.29 |
스마트 그리드 [smart grid] (0) | 2009.10.29 |
불가리아, Belene 원자력발전소 건설 추진동향 (0) | 2008.10.07 |